Construction method Geocell

Page view:

The laminated cell room opened (bedding can be some of the fibrous material, such as geotextiles, felt and other cells in the chamber below the ground depending on the circumstances).

Connected by nails or with stretching frame.

Loader filled with particulate filler until the grid is full and the room beyond the top, followed by vibration or rolling to complete the basic level.

At this point - grid system can support the variety of construction equipment, it can be applied directly thereon in a conventional manner to complete the surface layer.

Construction method